    The condition that a structure will be left in  should be agreed with the client during the survey planning/proposal stage. All clients will vary, with some planning to re-occupy on completion and others not. Some refurbishment or demolition surveys will be extremely intrusive and may take place during a phased demolition. Costs of making good/making safe, particularly if this involves other trades attending site, must also be agreed at the outset.